The power is OFF or the voltage is insufficient.
Ensure that the voltage is within the rated range.
Check the wiring. “Examples of wiring”
The SZ-V is in “Power Saving Mode”.
Turn power saving mode off
The SZ-V may be broken.
Replace the Display unit.
This is the start screen displayed after the power is turned on.
In approximately 8 seconds, the screen will transition to normal operation.
The SZ-V is under normal operation.
None.
The on-delay function is operating,
OSSD is OFF.
For details, see "SZ-V Series User's Manual".
The laser shutdown bank is selected.
Switch to a bank other than the laser shutdown bank.
The laser off input is ON,OSSD is OFF.
For details, see “SZ-V Series User's Manual”
The interlock function is operating, OSSD is OFF.
The SZ-V has detected a person or an object in the protection zone.
Terminate the interlock function by returning the SZ-V to a state in which it does not detect an object in the protection zone, and then perform reset operation using the reset input.
The interlock function is operating, OSSD is OFF.
Perform the reset operation to restart the SZ-V because the conditions for disabling the interlock are met.
Terminate the interlock function by performing the reset operation using the reset input.
The interlock function is operating, OSSD 1/2 is OFF.
Engage reset input 1/2 to restart the SZ-V because the conditions for terminating the interlock are met.
Terminate the interlock function by performing the reset operation using the reset input.
The interlock function is operating, OSSD 3/4 is OFF.
Engage reset input 3/4 to restart the SZ-V because the conditions for terminating the interlock are met
Terminate the interlock function by performing the reset operation using the reset input.
One of the scanner heads does not detect a reference point(s), OSSD is OFF
Ensure that the scanner head detects the reference points.
Muting state.
The safety function has been temporarily disabled and OSSD is ON.
None.
Override state.
The safety function has been temporarily disabled and OSSD is ON.
None.
Waiting for bank input state.
A bank has not been selected, OSSD is OFF.
Check that the bank input is correct.
The detection history is being saved.
The next detection history will not be saved until saving of the detection history is complete.
The SZ-V returns to the Normal Operation screen once the detection history has been saved.
Videos take about 30 seconds to save.
In preparation of saving the detection history.
The next detection history will not be saved until preparation is done
The SZ-V returns to the Normal Operation screen once the preparation is done.
The SZ-V is under normal operation.
Communicating with SZ Configurator
If the connection with SZ Configurator is terminated, the SZ-V returns to the Normal Operation screen.
Operations, such as transferring settings from the SZ Configurator are being performed.
OSSD is fixed to OFF
Once the operations from the SZ
Configurator are complete and the connection is terminated, the SZ-V returns to the Normal Operation screen.